Specialist Contractor for Sato Kogyo, the Main Contractor for the Design and Construction of the Sengkang–Punggol LRT (SPLRT) Depot Expansion and Associated Facilities under the Land Transport Authority (LTA), Singapore. The scope of works comprised the construction of approximately 1.0 km of elevated viaduct, serving as an additional spur line for the depot expansion. The works included the casting and delivery of precast segmental box girders (SBG) from Acre Works’ own precast yard in Kuala Lumpur, Malaysia, erection and launching using specialised bridge launching equipment and cranes, post-tensioning works, and all associated construction engineering and temporary works. A key engineering highlight of the project was the construction of a viaduct with an exceptionally tight horizontal curvature of 32.5 m radius, representing one of the most challenging curved viaduct alignments constructed in Singapore to date.
Client
Sato Kogyo (S) Pte. Ltd.
Location
Sengkang/Punggol, Singapore
Year
2023
Package
Precast segmental box girders 306 nos