100%
Transit System

MRT Line 2: SPP SBG 202 – Segment Casting and Delivery for Southern Section from
Package V206-V210

Project Information

Overview

Nominated Subcontractor (NSC) for the casting and supply of 6,399 precast segmental box girders (SBG) for the Klang Valley MRT Line 2 Project under Project Delivery Partner (PDP), MMC-Gamuda. The precasting works were carried out at Acre Works’ own casting yard in Hulu Langat, Selangor, utilising 6,399 segmental box girder mould production lines. The completed segments were supplied to five (5) different Main Contractors along the MRT alignment from Sungai Besi to Putrajaya.

Project Details

Client

V206 - Gadang Engineering (M) Sdn Bhd
V207 - Mudajaya Corporation Berhad
V208 - MTD Construction Sdn Bhd
V209 - Acre Works Sdn Bhd
V210 - Malaysian Resources Corporation Berhad

Location

Selangor, Malaysia

Year

2016

Package

Precast segmental box girders 6,399 nos