MRT Line 1:
Package V5 (Maluri Portal to Plaza Phoenix Station)

Project Information

Overview

Appointed as the Specialist Contractor for IJM Construction, the Main Contractor for the Klang Valley MRT Line 1 Package V5 at Cheras, Kuala Lumpur. The scope of works comprised the construction of three (3) long spans totalling approximately 0.6 km, forming part of the overall 5.4 km viaduct. The works included the casting of precast segmental box girders (SBG), erection and launching using segment lifters and cranes under the Balanced Cantilever Method (BCM), post-tensioning works, and all associated construction engineering and temporary works.

Project Details

Client

IJM Construction Sdn Bhd

Location

Kuala Lumpur, Malaysia

Year

2012

Package

Casting, launching and post tensioning works of 189 nos of segmental box girders (SBG) (special spans)