Specialist Contractor for Mudajaya Construction, the Main Contractor for the Klang Valley MRT Line 1 viaduct works between TTDI and Sunway Giza, Kuala Lumpur. The scope of works included the erection and launching of precast segmental box girders using launching girders imported from Italy for standard spans, and crane-assisted erection of two (2) long spans using the Balanced Cantilever Method (BCM). The works also included post-tensioning, associated construction engineering and temporary works. The two (2) long spans were constructed across the 1 Utama Shopping Centre junction and the New Klang Valley Expressway (NKVE).
Client
Mudajaya Corporation Bhd
Location
Selangor, Malaysia
Year
2012
Package
Launching and post tensioning (standard span 1,697 nos)
Casting, launching and post tensioning (long span 151 nos)