Specialist Contractor to Sunway Construction, the Main Contractor for the LRT Line 3 Project in Klang, Selangor. The scope of works involved the construction of three (3) long-span viaduct sections forming part of the overall 9.2 km alignment. The works included the casting of precast segmental box girders (SBGs), their erection and launching using segment lifters and cranes under the Balanced Cantilever Method (BCM), and the construction of a cast-in-situ bridge across the Klang River using the Form Traveller Method. The scope also encompassed post-tensioning works, together with all associated construction engineering and temporary works.
Client
Sunway Construction Sdn Bhd
Location
Selangor, Malaysia
Year
2019
Package
Precast segmental box girders 77 nos
Launching and post tensioning work of 167 nos
Cast in-situ box girder of 270.15m