Appointed as the Main Contractor under Turnpike (a subsidiary of Prolintas) for the design and construction of a section of the Sungai Besi–Ulu Kelang Elevated Expressway (SUKE), incorporating alternative designs for the mainline highway and interchange ramps. The scope of works involved complex viaduct structures comprising large-diameter single bored pile foundations, pier columns reaching heights of up to 27 metres, precast segmental crossheads, and precast U-girders and T-girders for the mainline and ramps. A key engineering highlight was the construction of cast-in-situ balanced cantilever spans using the Form Traveller Method across the Express Rail Link (ERL), KTM railway tracks and Besraya Highway. The project also included all associated construction engineering and temporary works.
Client
Turnpike Synergy Sdn Bhd
Location
Kuala Lumpur/Selangor, Malaysia
Year
2018
Package
Post-tensioning
Viaduct
Expressway
2.4 KM total length