Overview

Specialist Contractor for UEM Construction for the widening of approximately 7 km of the Penang Bridge in both directions. The scope of works included the casting and supply of 612 precast U-girders and I-girders, together with their erection and launching using two (2) crawler cranes mounted on marine barges. The marine operations were supported by tugboats for emergency assistance and rescue during adverse tidal and wave conditions. Specialised lifting and erection methods were adopted to ensure safe installation while minimising the impact on the existing bridge structure.

Project Details

Client

UEM Construction Sdn Bhd

Location

Penang, Malaysia

Year

2007

Package

612 nos of 40m U & I beams

7km beam casting and launching