Main Contractor under Malaysia Airports Holdings Berhad (MAHB) for the Design and Build Contract involving 5.2 km of elevated viaduct ramps serving the departure and arrival levels of Kuala Lumpur International Airport Terminal 2 (KLIA2). The scope of works included foundation and substructure works, pier columns, pier crossheads, precast T-girder production and erection, post-tensioning works, and all associated construction engineering and temporary works. A dedicated on-site precast casting yard was established for the production of 268 precast T-girders, which were subsequently erected and launched to form the elevated ramp structures.
Client
Malaysia Airports Holdings Berhad
Location
KLIA, Sepang, Selangor, Malaysia
Year
2010
Package
268 T beams
53 Precast curve U-beams
5.2KM bridge, bored piling, stone column, RE wall, pilecap, piers